AGIMP (Gas Main) Projects
| Description | Schedule to Start | Scheduled to Finish |
|---|---|---|
| Manoa Rd from Earlington Rd to Oxford Rd and Lenox Rd in between Manoa Rd in Haverford Township. Work will be completed on Monday through Friday from 9:00 a.m. – 3:00 p.m. | 09/2026 | 11/2026 |
| Spring Mill Ln and College Ave from Spring Mill Ln to Coopertown Rd in Haverford Township. Work will be completed on Spring Mill Ln Monday through Friday from 8:00 a.m. – 4:00 p.m. Work will be completed on College Ave Monday through Friday from 9:00 a.m. – 3:00 p.m. | 09/2026 | 11/2026 |
| Spring Mill Ln and College Ave from Spring Mill Ln to Coopertown Rd in Haverford Township. Work will be completed on Spring Mill Ln Monday through Friday from 8:00 a.m. – 4:00 p.m. Work will be completed on College Ave Monday through Friday from 9:00 a.m. – 3:00 p.m. | 09/2026 | 11/2026 |
| Urgent gas main replacement by PECO. Pickwick Rd btw. Devon Rd & Covington Rd. Monday - Friday, 8:30 AM to 5:30 PM, Saturday 8:30 AM - 5:00 PM. | 09/2026 | Mid 10/2026 |
| Patching, Milling, and Paving will take place on Lawson Ave between Edgewood Ave to Merion Ave by PennDOT | 09/2026 | TBD |
| Oxford Rd from Earlington Rd to Manoa Rd in Haverford Township. Work will be completed on Monday through Friday from 7:00 a.m. – 3:00 p.m. | 08/2026 | 11/2026 |
| Kenmore Rd from Allston Rd to Earlington Rd - Work will be completed on Monday through Friday from 7:00 a.m. – 3:00 p.m. | 06/2026 | 10/2026 |
| Wood Ln from Bellemead Ave to Belvedere Ave, on Belvedere Ave from Wood Ln to Fairfield Rd, on Manor Rd from Wood Ln to Harvard Rd and on Fairfield Rd from Belvedere Ave to Bellemead Ave. | 03/2026 | 10/2026 |
| Earlington Rd from Wynne Ave to E. Township Line Rd in Haverford Township | 03/2026 | 11/2026 |
| Earlington Rd from Mill Rd to Wynne Ave | 05/2026 | N/A |
| Preston Ave from E Railroad Ave to Haverford Rd, Buck Lane from E Railroad Ave to Haverford Rd in Haverford Township | 03/2026 | 11/2026 |
| College Ave from Tunbridge Rd to Bridge Crossing, Spring Mill Ln from College Ave to Dead End | 04/06/2026 | 10/2026 |
| College Ave from Haverford Rd to Bridge Crossing, Haverford Rd from College Ave to Preston Ave, West Ave from | 06/22/2026 | 10/2026 |
| Fairfield Rd from Belvedere Ave to Bellemeade Ave, Belvedere Ave from Wood Ln to Fairfield Rd, Wood Ln from Belvedere Ave to Bellemeade Ave, Manor Rd from Wood Ln to Harvard Rd | 06/01/2026 | N/A |
| Twin Oaks Dr from Glen Arbor Rd to Manoa Rd | 10/12/2026 | 12/2026 |
| Railroad Ave from Martin Ave to Reg Station | 09/07/2026 | 102026 |
| Railroad Ave to Bridge Crossing | 06/15/2026 | 10/23/2026 |
| Manoa Rd from Oxford Rd to Earlington Rd, Lenox Rd from Manoa Rd to Pembroke Rd | 09/21/2026 | 11/27/2026 |
| Kenmore Rd from Earlington Rd to Allston Rd, Pembroke Rd from Kenmore Rd to Oxford Rd, | 07/13/2026 | 11/20/2026 |
| Earlington Road from Wynne Ave to Mill Rd | 02/09/26 | 08/21/26 |
| Meadowbrook Ln from Township Line Road | 07/2025 | TBD |
| College Ave from Darby Rd to Coopertown Rd | 10/2025 | TBD |
| Landover Rd - Upgrades to underground cable lines near the Bryn Mawr Peco Substation. The work will take place Monday - Friday, 9:00 A.M. - 3:00 P.M. for 10 weeks. | TBD | TBD |
| Upland Rd from N. Eagle Rd to Roosevelt Ave | 09/2025 | 11/2026 |
• Updated 09/11/2026
AQUA - Water Main Replacements
| Description | Schedule to Start | Scheduled to Finish |
|---|---|---|
| Township Line Rd between Cobbs St and West Chester Pike in Haverford & Upper Darby Townships | 03/22/2026 | Summer 2026 |
| Haverford Road in both directions at the intersection with Landover Road. A weekday lane closure with flagging is scheduled. Weekdays, 9:00 AM to 3:00 PM. | N/A | N/A |
| Landover Road between Haverford Road and Radwyn Apartments Entrance/Gaynor Rd.9:00 AM to 3:00 PM. Residents will have access to their properties, but at times may need to enter from different directions. During the closure, motorists will be directed to use Haverford Road, College Avenue, and Coopertown Road. Local access will be maintained up to the work zone. *The trench will be covered with temporary blacktop at the end of each workday. Questions - AQUA (610) 328-7713 | N/A | N/A |
• Updated 08/17/2026 - No changes 09/11/26
PECO Cable/Conduit Projects
| Description | Schedule to Start | Scheduled to Finish |
|---|---|---|
| Greenbriar Lane, Crescent Hill Dr, Rose Tree Ln, Walnut Hill Ln and Westgate Rd | 02/02/2024 | N/A |
| 4th & 5th Wards | 08/01/2024 | 11/30/2024 |
| Railroad Avenue between Polo Road and Rugby Road | 09/30/2024 | N/A |
• Updated 08/26/2025 - No changes 09/11/26